A few weeks into June, with nothing other than a new wall accomplished, I admitted to myself that having the room ready for July summer classes was a bit ambitious. Could we have held classes with a boombox on the carpet? Sure. Was that the first impression of the new and exciting space I wanted to give my clients. Uh, absolutely not.
So, onto painting. But wait! First the other studio location has to have a pipe burst! And flood the entire space! And ruin lots of things! And require insurance inspectors and summer camp last-minute changes and new rugs and potentially ruined marley! Because chaos!
::deep breath::
So that was a fun weekend of clean-up and tears and then realizing that a pipe bursting during summer and destroying a bunch of old costumes is not the worst thing in the world, even if it is inconvenient and a pain to clean up (imagine if it happened a week before recital and ruined THOSE costumes?!). It is also just a bit disconcerting to find your entire space covered in water.
But, back to the matter at hand – oh yeah, I was supposed to be painting, not mopping up water.
And look, a new window!
Making progress…
To Do List
X Connect spaces
X Build waiting room wall
X Waiting room window
X Paint waiting room
X Paint dance room
– Install dance floor
– Furnish waiting room
– Buy sound system
– Ballet barres in dance room
– Order and install mirrors
Next up… flooring!
More power to ya! Sometimes, though, setbacks make us really dig in and work for our dreams. In the end, it will mean so much more. Good luck and thanks for sharing!